@softwareengineerprogrammer softwareengineerprogrammer commented Dec 22, 2025

Description

  1. Addresses Project Cape Construction Timelines & Reservoir Engineering Updates NatLabRockies/GEOPHIRES-X#443
  2. Addresses Remove or clarify SAM-EM project payback period NatLabRockies/GEOPHIRES-X#413 (8764602)
  3. Addresses SAM Economic Models ITC should be derived from cash flow NatLabRockies/GEOPHIRES-X#404 (SAM-EM ITC output #124)

Web interface links:

  1. Fervo_Project_Cape-5 (500 MW/Phases I & II): https://gtp.scientificwebservices.com/geophires/?shared-geophires-result-id=5d331dd4-8cc3-497f-8197-0ef21116b4cb
  2. Fervo_Project_Cape-6 (100 MW/Phase I): https://gtp.scientificwebservices.com/geophires/?shared-geophires-result-id=ab59f0ab-133b-4d5f-b0da-c7d9699dafc0

TODO

Deferred to main repo and/or follow-up PR

  1. 🚧 SME review (reservoir engineering)
    1. Explore recalibration to 2 redrillings instead of 3 - either via more stimulated fracture surface area or custom reservoir profile based on Singh et al.
  2. 🚧 Calibrate Fervo_Project_Cape-6: 866b4c8, d7bcda0
    1. Strip (irrelevant) param comments: 632e6b4
  3. Confirm levelized cost metrics per SAM-EM Multiple Construction Years: SAM SME Design Review NatLabRockies/GEOPHIRES-X#444: 44b9bf1
  4. Sensitivity analysis chart tweaks:
    1. Flow rate text overlap
    2. Link titles (on hover)
  5. Remove preview designation (867e7c1)
  6. Add a CHANGELOG entry for 3.11.4
  7. Document inflation rate assumption is higher than ATB (or use ATB value)
  8. Add relevant reservoir design figures from https://www.resfrac.com/wp-content/uploads/2025/06/Singh-2025-Fervo-Project-Cape.pdf
    1. image
    2. image
    3. image

Completed

  1. Fix layout.html changes relevant to ‼️ Organization name change has broken documentation links NatLabRockies/GEOPHIRES-X#454:
  2. Clarify image: 5fe4429
  3. Clarify 103 kg/s flow rate (Avg net retune closer to 500 MW [2026-01-19] #127): 5c48513
  4. Incorporate ATB updates: https://atb.nrel.gov/electricity/2024b/geothermal
  5. Royalties (BLM): 469b250
  6. Sensitivity analysis: address why higher flow rates != better economics: 632e79e
  7. Reference https://www.resfrac.com/wp-content/uploads/2025/06/Singh-2025-Fervo-Project-Cape.pdf: 0b7da6c
  8. Calibrate exploration cost to https://atb.nrel.gov/electricity/2024b/geothermal: b94b01f
    1. Created tracking issue to update GEOPHIRES correlation :Update exploration cost correlation according to 2024b ATB NatLabRockies/GEOPHIRES-X#447
  9. Documentation and references
    1. Drilling & stim costs clarifications in Inputs: 64da798, 77e5fd2
    2. Clarify calibration of drawdown/redrilling wrt 1-2% expected annual decline: Technical results graphs #125, Production temperature technical results graph #126
    3. Construction CAPEX schedule
    4. Approach & Methodology update: Clarify SOAK vs. FOAK vs. NOAK: 1e960e4
    5. Describe case study use cases e.g. as a template for custom modeling: 1e960e4
    6. ITC
    7. TOD/ambient temp: 3f96592
    8. OCC vs total capex: a791d54
  10. Sensitivity analysis: https://github.com/scientific-web-services/geophires-fpc4-sensitivity-analysis
  11. Surface temperature fine-tune based on Project InnerSpace GeoMap: 9af9f1d
  12. Multiple construction years: Update Fervo_Project_Cape-4 based on publicly stated timelines - https://fervoenergy.com/fervo-energy-raises-462-million-series-e-to-accelerate-geothermal-development-and-meet-surging-energy-demand-with-clean-firm-power/
    1. Phase II: 500 MW: Fervo_Project_Cape-4
    2. Phase I: 100 MW: Fervo_Project_Cape-5: 71607b7
  13. Reservoir engineering updates
    1. ~8.5" ID
    2. Flow rate
    3. Fracture surface area
    4. PI/II instead of impedance
    5. Number of Fractures per Stimulated Well
    6. Increased lateral length (adjust fracture separation accordingly)
  14. Higher discount & bond rates

Testing & Verification

  1. Unit tests added: Retains test for previous version: https://github.com/softwareengineerprogrammer/GEOPHIRES/pull/117/changes#diff-77443b51920606ff05244e83370cb4bbd78fb8ee13076d9356d5051c2c9fbef5
  2. Unit tests updated: https://github.com/softwareengineerprogrammer/GEOPHIRES/pull/117/changes#diff-35ea0c0b80463f35958a7d1d7396bad7ad397a7c8e8d96a49da5b90e756c7c7c
  3. Manually tested
fervo_project_cape-5-sensitivity-analysis-lcoe fervo_project_cape-5-sensitivity-analysis-irr fervo_project_cape-5-sensitivity-analysis-project_npv

Change Checklist:

Observe the following checklist items if your change includes a new version (see versioning notes and version management docs).

After merging:

  1. Push tag(s) to GitHub: git push origin refs/tags/vM.m.P
  2. Post a change announcement to the GEOPHIRES Change Announcements Discussion (example). Markdown template:
M.m.p: [TITLE](https://github.com/NREL/GEOPHIRES-X/pull/PR-NUMBER) | [release](https://github.com/NREL/GEOPHIRES-X/releases/tag/vM.m.P)

@softwareengineerprogrammer softwareengineerprogrammer changed the title Project Cape MCY and Reservoir Engineering updates Project Cape Construction (MCY) and Reservoir Engineering updates Jan 1, 2026
@softwareengineerprogrammer softwareengineerprogrammer changed the title Project Cape Construction (MCY) and Reservoir Engineering updates Project Cape Construction Timeline (MCY) and Reservoir Engineering updates Jan 1, 2026
@softwareengineerprogrammer softwareengineerprogrammer changed the title Project Cape Construction Timeline (MCY) and Reservoir Engineering updates Project Cape Multi-Year Construction Timeline and Reservoir Engineering updates Jan 6, 2026
@softwareengineerprogrammer softwareengineerprogrammer changed the title Project Cape Multi-Year Construction Timeline and Reservoir Engineering updates Fervo_Project_Cape-4 Multi-Year Construction Timeline and Reservoir Engineering updates Jan 6, 2026
@softwareengineerprogrammer softwareengineerprogrammer changed the title Fervo_Project_Cape-5: Multi-Year Construction Timeline and Reservoir Engineering updates Fervo_Project_Cape-5: Multi-Year Construction Timeline and Reservoir Engineering updates; SAM-EM Payback Period; SAM-EM ITC Jan 24, 2026
@softwareengineerprogrammer softwareengineerprogrammer changed the title Fervo_Project_Cape-5: Multi-Year Construction Timeline and Reservoir Engineering updates; SAM-EM Payback Period; SAM-EM ITC [v3.11] Fervo_Project_Cape-5: Multi-Year Construction Timeline and Reservoir Engineering updates; SAM-EM Payback Period; SAM-EM ITC Jan 24, 2026
@softwareengineerprogrammer softwareengineerprogrammer changed the title [v3.11] Fervo_Project_Cape-5: Multi-Year Construction Timeline and Reservoir Engineering updates; SAM-EM Payback Period; SAM-EM ITC [v3.11] Fervo_Project_Cape-5: Multi-Year Construction Timeline and Reservoir Engineering updates; SAM-EM Payback Period; SAM-EM ITC Jan 24, 2026
@softwareengineerprogrammer softwareengineerprogrammer merged commit 3d284f1 into main Jan 24, 2026
8 of 9 checks passed
@softwareengineerprogrammer softwareengineerprogrammer changed the title [v3.11] Fervo_Project_Cape-5: Multi-Year Construction Timeline and Reservoir Engineering updates; SAM-EM Payback Period; SAM-EM ITC [v3.11.4] Fervo_Project_Cape-5: Multi-Year Construction Timeline and Reservoir Engineering updates; SAM-EM Payback Period; SAM-EM ITC Jan 24, 2026
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Labels

None yet

Projects

None yet

Development

Successfully merging this pull request may close these issues.

2 participants