I have a routing operation which has two time_per operations in it.
I have a resource pool "Operators" with 2 resources, equal cost and efficiency.
The two time_per operations are linked to the "Operators" pool.
When executing the planner, it allways choose resource A. No problem there since there isn't any difference between resource A and B.
But when I enter a partial unavailability for resource A, the solver puts the sales order late and still pick Resource A instead of picking resource B which is fully available and it would result in meeting the Demand in time.
reacted with thumbs up emoji reacted with thumbs down emoji reacted with laugh emoji reacted with hooray emoji reacted with confused emoji reacted with heart emoji reacted with rocket emoji reacted with eyes emoji
Uh oh!
There was an error while loading. Please reload this page.
-
Hi !
I have a routing operation which has two time_per operations in it.
I have a resource pool "Operators" with 2 resources, equal cost and efficiency.
The two time_per operations are linked to the "Operators" pool.
When executing the planner, it allways choose resource A. No problem there since there isn't any difference between resource A and B.
But when I enter a partial unavailability for resource A, the solver puts the sales order late and still pick Resource A instead of picking resource B which is fully available and it would result in meeting the Demand in time.
Am I doing something wrong in the configuration ?
Thanks !
Ernesto.